| Coastal Virginia Offshore Wind (CVOW) Commercial Project | VA | | Dominion Energy Inc. | Offshore Wind Turbine | 2,640 | Jan 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Chokecherry and Sierra Madre Wind | WY | Carbon | Power Company of Wyoming LLC | Onshore Wind Turbine | 1,303.2 | Dec 2032 | (U) Under construction, less than or equal to 50 percent complete |
| Sunstone Solar | OR | Morrow | Sunstone Solar, LLC | Batteries | 1,200 | Dec 2027 | (L) Regulatory approvals pending. Not under construction |
| Sunstone Solar | OR | Morrow | Sunstone Solar, LLC | Solar Photovoltaic | 1,200 | Dec 2027 | (L) Regulatory approvals pending. Not under construction |
| Pepper Hammock Solar and Storage | GA | Wayne | BrightNight Power | Solar Photovoltaic | 1,200 | Sep 2029 | (L) Regulatory approvals pending. Not under construction |
| Steward Creek Solar Phase 1 | IL | Lee | TerraForm Power Operating, LLC | Solar Photovoltaic | 1,200 | Dec 2029 | (P) Planned for installation, but regulatory approvals not initiated |
| Vista Sands Solar | WI | Portage | Vista Sands Solar LLC | Solar Photovoltaic | 1,182 | Dec 2028 | (L) Regulatory approvals pending. Not under construction |
| Project Matador Nuclear | TX | Carson | Fermi Nuclear | Nuclear | 1,117 | Dec 2031 | (P) Planned for installation, but regulatory approvals not initiated |
| Project Matador Nuclear | TX | Carson | Fermi Nuclear | Nuclear | 1,117 | Dec 2031 | (P) Planned for installation, but regulatory approvals not initiated |
| Project Matador Nuclear | TX | Carson | Fermi Nuclear | Nuclear | 1,117 | Dec 2032 | (P) Planned for installation, but regulatory approvals not initiated |
| Project Matador Nuclear | TX | Carson | Fermi Nuclear | Nuclear | 1,117 | Dec 2032 | (P) Planned for installation, but regulatory approvals not initiated |
| Deschutes Solar and BESS | OR | Wasco | DECH bn, LLC | Solar Photovoltaic | 1,000 | Nov 2029 | (L) Regulatory approvals pending. Not under construction |
| Deschutes Solar and BESS | OR | Wasco | DECH bn, LLC | Batteries | 1,000 | Nov 2029 | (L) Regulatory approvals pending. Not under construction |
| Sycamore Riverside Energy, LLC | IN | Sullivan | Invenergy Services LLC | Natural Gas Fired Combustion Turbine | 964 | Mar 2029 | (P) Planned for installation, but regulatory approvals not initiated |
| Sunrise Wind | NY | Suffolk | Orsted Wind Power North America LLC | Offshore Wind Turbine | 924 | Oct 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Pepper Hammock Solar and Storage | GA | Wayne | BrightNight Power | Solar Photovoltaic | 900 | Sep 2029 | (L) Regulatory approvals pending. Not under construction |
| Chokecherry and Sierra Madre Wind | WY | Carbon | Power Company of Wyoming LLC | Onshore Wind Turbine | 849.6 | Dec 2031 | (U) Under construction, less than or equal to 50 percent complete |
| Chokecherry and Sierra Madre Wind | WY | Carbon | Power Company of Wyoming LLC | Onshore Wind Turbine | 844.2 | Dec 2031 | (U) Under construction, less than or equal to 50 percent complete |
| Empire Wind 1 | NY | Kings | Empire Offshore Wind LLC | Offshore Wind Turbine | 810 | Sep 2027 | (V) Under construction, more than 50 percent complete |
| Cedar Island Solar LLC | OR | Sherman | Cedar Island Solar LLC | Solar Photovoltaic | 800 | Dec 2031 | (L) Regulatory approvals pending. Not under construction |
| Viola Generating Station | KS | Sumner | Evergy Kansas Central, Inc | Natural Gas Fired Combined Cycle | 765 | Jan 2029 | (T) Regulatory approvals received. Not under construction |
| McNew Generating Station | KS | Reno | Evergy Kansas Central, Inc | Natural Gas Fired Combined Cycle | 765 | Jan 2030 | (T) Regulatory approvals received. Not under construction |
| Legend Power Station | TX | Jefferson | Entergy Texas Inc. | Natural Gas Fired Combined Cycle | 754 | Jul 2028 | (L) Regulatory approvals pending. Not under construction |
| Mill Creek (KY) | KY | Jefferson | Louisville Gas & Electric Co | Natural Gas Fired Combined Cycle | 740 | Jun 2027 | (V) Under construction, more than 50 percent complete |
| CPV Basin Ranch Energy Center | TX | Ward | CPV Basin Ranch | Natural Gas Fired Combined Cycle | 722.5 | Feb 2029 | (U) Under construction, less than or equal to 50 percent complete |
| CPV Basin Ranch Energy Center | TX | Ward | CPV Basin Ranch | Natural Gas Fired Combined Cycle | 722.5 | Feb 2029 | (U) Under construction, less than or equal to 50 percent complete |
| Cedar Bayou 5 | TX | Chambers | Cedar Bayou 5 LLC | Natural Gas Fired Combined Cycle | 721 | Aug 2028 | (U) Under construction, less than or equal to 50 percent complete |
| Revolution Wind | RI | Washington | Orsted Wind Power North America LLC | Offshore Wind Turbine | 715 | Nov 2026 | (V) Under construction, more than 50 percent complete |
| Libra Solar | NV | Lyon | Libra Solar LLC | Batteries | 700 | Dec 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Libra Solar | NV | Lyon | Libra Solar LLC | Solar Photovoltaic | 700 | Dec 2027 | (U) Under construction, less than or equal to 50 percent complete |
| IP Roman Wind | TX | Deaf Smith | Intersect USA, LLC | Onshore Wind Turbine | 670.5 | Sep 2028 | (L) Regulatory approvals pending. Not under construction |
| Sandow Lakes Energy Station | TX | Lee | SL Energy Power Plant I, LLC | Natural Gas Fired Combined Cycle | 645 | Oct 2028 | (P) Planned for installation, but regulatory approvals not initiated |
| Sandow Lakes Energy Station | TX | Lee | SL Energy Power Plant I, LLC | Natural Gas Fired Combined Cycle | 645 | Dec 2028 | (P) Planned for installation, but regulatory approvals not initiated |
| Tehuacana Creek Solar | TX | Navarro | Parliament Energy Holdings LLC | Solar Photovoltaic | 644.8 | May 2027 | (V) Under construction, more than 50 percent complete |
| Lincoln Land Energy Center | IL | Sangamon | Lincoln Land Energy Center LLC | Natural Gas Fired Combined Cycle | 638.4 | Jun 2030 | (P) Planned for installation, but regulatory approvals not initiated |
| Lincoln Land Energy Center | IL | Sangamon | Lincoln Land Energy Center LLC | Natural Gas Fired Combined Cycle | 638.4 | Jun 2030 | (P) Planned for installation, but regulatory approvals not initiated |
| Haymaker Hybrid | MT | Wheatland | Haymaker Energy Project LLC | Onshore Wind Turbine | 630 | Oct 2031 | (P) Planned for installation, but regulatory approvals not initiated |
| Illinois Generation LLC | IL | Livingston | Pattern Operators LP | Onshore Wind Turbine | 616.5 | Apr 2028 | (T) Regulatory approvals received. Not under construction |
| Shady Hills Combined Cycle Facility | FL | Pasco | Shady Hills Energy Center, LLC | Natural Gas Fired Combined Cycle | 612 | Nov 2026 | (TS) Construction complete, but not yet in commercial operation |
| Short Creek Solar | TX | Wichita | Wichita Solar I, LLC | Solar Photovoltaic | 606.4 | Mar 2028 | (L) Regulatory approvals pending. Not under construction |
| Singing Grass Wind | CO | Kit Carson | Public Service Co of Colorado | Onshore Wind Turbine | 603 | Sep 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Danish Fields Solar, LLC | TX | Wharton | Danish Fields Solar, LLC | Solar Photovoltaic | 600 | Sep 2026 | (TS) Construction complete, but not yet in commercial operation |
| Swenson Solar | TX | Stonewall | Swenson Solar LLC | Solar Photovoltaic | 600 | Nov 2026 | (U) Under construction, less than or equal to 50 percent complete |
| Clear Fork Creek Solar and BESS SLF | TX | Wilson | Clear Fork | Batteries | 600 | Mar 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Clear Fork Creek Solar and BESS SLF | TX | Wilson | Clear Fork | Solar Photovoltaic | 600 | Mar 2027 | (U) Under construction, less than or equal to 50 percent complete |
| Arkansas Cypress Solar Station | AR | Jefferson | Entergy Arkansas LLC | Solar Photovoltaic | 600 | Jan 2029 | (P) Planned for installation, but regulatory approvals not initiated |
| Bellflower Solar (VA) | VA | Brunswick | Dominion Renewable Energy | Solar Photovoltaic | 600 | Jan 2030 | (P) Planned for installation, but regulatory approvals not initiated |
| GREC | OK | Mayes | Grand River Dam Authority | Natural Gas Fired Combustion Turbine | 594 | Sep 2026 | (TS) Construction complete, but not yet in commercial operation |
| Hecate Energy Cider Solar LLC | NY | Genesee | Greenbacker Renewable Energy Corporation | Solar Photovoltaic | 557 | Oct 2026 | (U) Under construction, less than or equal to 50 percent complete |
| Chokecherry and Sierra Madre Wind | WY | Carbon | Power Company of Wyoming LLC | Onshore Wind Turbine | 553.5 | Dec 2033 | (U) Under construction, less than or equal to 50 percent complete |